CEDAR RIDGE POWER FACILITY

img

ROLE:

DESIGN BUILDER, GENERAL CONTRACRTOR

Krospeson Construction Group, Inc was hired to design build the Administration and Control Building at Towantic Power Plant in Oxford, CT. We offer top-notch commercial construction services to help you build or renovate your business property with ease.  The building was designed as a pre-engineered metal building to house the Aux Boiler, Electrical Room, and Warehouse serving the entire power plant.  The progress we made on the Admin Control Building led to Gemma Power Systems to hire us to erect (2) Boiler Feed Pump Buildings and associated Pipe Rack, as well as the building envelope of the Steam Turbine Generator building.

Location

Building Size

Architect

Role

Cost

Schedule

Oxford,  CT

7,000sf 

DeStafano & Chamberlain, Inc.

Design Builder for Admin Building

5.4 Million Dollar

10 Months